120 m hoarding on an exposed corner
A CBD construction site with one corner fully open to harbour wind. The hoarding had to be wind-rated, fire-rated, and pass inspection on the morning it went up.
The brief
Wrap a 120 linear metre construction hoarding around a city block, including a corner with no shelter from the prevailing wind. The graphics were a property developer's campaign — render, project name, completion date, agent details.
The constraint
Three constraints arrived together. The corner was exposed, so solid banner there would have acted as a sail. The site was in a public realm, so the media needed a fire rating and the certificate had to be on site at build-up. And the graphics were to be installed in a single weekend, which meant no second chance at the colour.
There was also a planning condition: the render image could not be distorted. Scaling a building visual to fit a 2.4 m drop would have made a 30-storey tower look squat, and the planning authority had already approved the proportions.
What we did
We split the run: solid FR banner at pedestrian level where the surface is sheltered and the graphics are read close up, and 30 % vented FR mesh on the upper band and around the exposed corner. Same artwork family, two media, planned so the transition fell on a horizontal line rather than through the render.
Panel widths were planned backwards from the render: we kept the building image inside single panels and put the joins over sky and foreground. The drop stayed at 2.4 m so the tower proportions held.
Every panel got a welded hem and stainless eyelets at 400 mm centres, with doubled eyelets at corners. The batch test report, type certificate and a material offcut went into the document wallet with the packing list.
Specification
| Item | Spec | Qty |
|---|---|---|
| Lower band, solid | 510 gsm FR banner, B1 / M1, welded hem, eyelets 400 mm | 170 m² |
| Upper band and corner | 270 gsm FR mesh, 30 % airflow | 120 m² |
| Fire documentation | Type certificate + batch test report + offcut | 1 wallet |
| Seam plan | Joins placed outside render, 5 mm overlap on batten | drawing |
What it cost and how long
Eighteen days from approval to arrival, of which ten were sea freight. Production was five working days because the run mixed two media and two finishing lines.
Sea freight was chosen over air deliberately: at 290 m² the air premium would have exceeded the cost of the print, and the site programme allowed the transit time.
What we would repeat
The seam plan, drawn before artwork rather than after. It is the cheapest intervention on a large hoarding and the one most often skipped — and a render split through the middle of a tower is a reprint, not a conversation.
Client names are withheld on request — design and brand accounts ship under their own labelling. Figures are as invoiced for the project and include finishing; freight is quoted separately.