Trade show graphics: a checklist that survives the venue
Every hall has rules that are cheaper to read than to discover on build day. Here is the checklist we run with exhibitors before printing.
Send size, quantity and destination. Itemised quote in 12 working hours.
Request a quote
Build day is a bad time to learn that the hall requires fire-retardant media, that the rigging height is 4 m rather than 6 m, or that the shell scheme's clear height is 2.48 m. All three are knowable weeks earlier, and all three change what you print.
1. Get the stand drawing before you design
Shell schemes differ. A standard 3 × 3 m package usually gives 2.48 m clear height, a backwall and two side walls with a rail system, plus a fascia board with your name. That fascia is often the only place the organiser allows a logo at height — printing your own 3 m banner over it may breach the contract.
Ask the organiser for: clear height, rail or hook system, whether walls are fabric or panel, whether rigging is included, and the maximum hanging load.
2. Standard sizes, and why to use them
| Item | Size | Note |
|---|---|---|
| Backwall panel | 3 × 2.5 m (pole pocket) | 2.5 m allows for the pocket take-up on a 2.48 m opening |
| Side return | 1 × 2.5 m each | Eyelets every 50 cm |
| Counter wrap | 2 × 0.9 m | Measure the counter, not the drawing |
| Hanging banner | 3 × 1 m or 2 × 1 m | Double sided blockout |
| Roll-up | 85 × 200 cm | Fits inside a 1 m aisle |
| Foam panels | A1 (594 × 841 mm) | Easy to carry as luggage |
Using standard sizes matters for two reasons: they fit the frame you have already paid for, and if a panel is damaged in transit a replacement can be printed and couriered overnight from a standard file.
3. Fire retardancy is a venue requirement, not a preference
Most exhibition halls in Europe, the Middle East and Asia require printed materials to meet a fire standard — B1 / DIN 4102 in Germany, M1 in France, BS 5867 or EN 13501 in the UK, and local equivalents elsewhere. The venue may ask for a certificate, and inspectors do spot-check on build day.
Specify FR media at the quotation stage: it adds roughly $1.80/m² and the test report ships with the goods. Printing on standard media and hoping is the single most common cause of a stand being covered up on opening morning.
4. Hanging banners: rigging rules
- Check the maximum hanging load per rigging point — usually 50–100 kg in a hall, lower in a hotel.
- Hanging banners need a frame or a weighted bar; a printed banner alone will not hang flat.
- Height matters for artwork: a banner read from the aisle below needs 100 mm cap height minimum.
- Book rigging with the venue in advance; it is rarely available on build day.
5. Artwork deadlines, working backwards
From an opening date, work back: 2 days for venue build, 3–5 days for freight (air) or 25–40 (sea), 3–4 days production, 2 days for proof approval. That puts artwork approval roughly three weeks before the show for air freight, and six to eight weeks for sea.
6. The crate list
What actually goes in the case, in the order the team will need it:
- Numbered panels matching a printed layout drawing
- Cable ties, hook-and-loop tape, double-sided tape, a staple gun
- Spare eyelets and a setting tool
- Roll-ups in bags, with their bases wrapped separately
- A4 colour proof, so any dispute about colour is settled against the approved sheet
- Touch-up pen for scuffed edges on rigid panels
7. What we ask before quoting a booth
Stand drawing, hall name, show dates, whether FR is required, the destination (venue direct or forwarder), and whether the graphics must be reusable for the next show. The last one changes the recommendation: a reusable SEG fabric system costs more than PVC panels once, and less from the second show onward.
Related questions
At most international venues, yes. B1 / M1 or the local equivalent is commonly required, and inspectors may ask for the certificate on build day. We supply FR media and the test report with the shipment.
A 3 × 2.5 m backwall with pole pockets, on a stand with 2.48 m clear height. The extra 20 mm is taken up by the pocket so the panel hangs without a gap.
Three weeks before the show for air freight, six to eight weeks for sea. Production is 3–4 days; freight and proof approval consume the rest.